Figure 2: Value-stream map for image documentation before process improvement. The previous process had a total time of 480-500 minutes, of which 68-132 minutes were non-value-added time. VA indicates value-added activities; NVA, non-value-added activities; PCE, process-cycle efficiency

Figure 2: Value-stream map for image documentation before process improvement. The previous process had a total time of 480-500 minutes, of which 68-132 minutes were non-value-added time. VA indicates value-added activities; NVA, non-value-added activities; PCE, process-cycle efficiency